Hinzufügen von Werktagen in Oracle SQL

Sie können dies versuchen:

select max(date_field_two) as date_field_two
  from
 (
 select date'2018-08-30'+  
    cast(case when to_char(date'2018-08-30'+level,'D','NLS_DATE_LANGUAGE=ENGLISH') 
                                              in ('6','7') then 
            0
          else
            level
          end as int) as date_field_two, 
 sum(cast(case when to_char(date'2018-08-30'+level,'D','NLS_DATE_LANGUAGE=ENGLISH')  
                                               in ('6','7') then 
            0
          else
            1
          end as int)) over (order by level) as next_day
      from dual
    connect by level <= 20*1.5 
-- 20 is the day to be added, every time 5(#of business days)*1.5 > 7(#of week days)
-- 7=5+2<5+(5/2)=5*(1+1/2)=5*1.5 [where 1.5 is just a coefficient might be replaced a greater one like 2]
-- so 4*5*1.5=20*1.5 > 4*7 
  )    
 where next_day = 20;

 DATE_FIELD_TWO
-----------------
   27.09.2018

indem Sie connect by dual verwenden Klausel.

P.S. Ignoriert den Fall für gesetzliche Feiertage, die sich von einer Kultur zur anderen unterscheiden, je nachdem, ob sich die Frage nur auf Wochenenden bezieht.

Rextester-Demo

Bearbeiten : Angenommen, Sie haben am 25.09.2018 und am 26.09.2018 (in dieser Reihe von Tagen) nationale Feiertage, dann ziehen Sie Folgendes in Betracht:

select max(date_field_two) as date_field_two
  from
 (
 select date'2018-08-30'+  
        (case when to_char(date'2018-08-30'+level,'D','NLS_DATE_LANGUAGE=ENGLISH') 
                                              in ('6','7') then 
               0
              when date'2018-08-30'+level in (date'2018-09-25',date'2018-09-26') then
               0
              else
               level
              end) as date_field_two, 
 sum(cast(case when to_char(date'2018-08-30'+level,'D','NLS_DATE_LANGUAGE=ENGLISH')  
                                               in ('6','7') then 
                0
               when date'2018-08-30'+level in (date'2018-09-25',date'2018-09-26') then
                0 
               else
                1
               end as int)) over (order by level) as next_day
      from dual
    connect by level <= 20*2 
  )    
 where next_day = 20;

 DATE_FIELD_TWO
-----------------
   01.10.2018

die wie in diesem Fall am nächsten Tag wiederholt wird, es sei denn, dieser Feiertag fällt mit dem Wochenende zusammen.